5.16.2. Removal, check and installation of the pneumatic valve рециркуляции the fulfilled gasesThe key on 12 is required to you.
|
|
1. Disconnect a vacuum hose from the pneumatic valve рециркуляции the fulfilled gases.
|
2. Turn out two bolts of fastening of the valve to an inlet pipe …
|
3. … also remove the valve.
THE NOTE
Connection of the valve with an inlet pipe is condensed by a lining. At each dismantling of connection replace a sealing lining new.
|
4. For valve check submit in any way depression to its vacuum chamber and observe of moving плунжера (it is shown by an arrow). If плунжер remains motionless, replace the valve.
5. Establish the pneumatic valve рециркуляции the fulfilled gases in an order, the return to removal.
|